Neuartige Abluftanlage für INEOS Granuform Betrieb

Picture 14: Investigation on the best possible course of the waste air pipe

Bild 14 Autokran vor Betrieb IMG_0338[1]

The pipe which collects the emissions from the plant and leads them to the waste air purification unit must cross a street next to the plant in order to reach the unit. However, in this street the truck-mounted crane must also be installed in case of a major repair inside the factory. For this reason, tests were performed using such a truck-mounted crane in order to find the best crossing for the pipe.  

 