The concrete work is finished and the pipe construction starts. A pipe for the supply with natural gas is installed to the place of the future waste air purification unit and the installation of the waste air pipe with a diameter of 1,20 m begins. This pipe was delivered in several parts and is now installed on bearing supports.
Also, a visit was made to the company Kümmerling for an exchange on experiences on energy saving measures and waste air reductions.